An AI 100-day plan should pick two or three workflows, record their baseline in the first month, and report measured dollars by day 100. Anything broader turns into a list of pilots with no result at the board meeting.
Why the first 100 days matter
Bain’s 2026 private equity report gives the hurdle. A typical deal now needs about 10% to 12% EBITDA growth a year to return 2.5 times invested capital over five years. Operations must supply most of that growth, and the clock starts at close.
Most AI work does not reach the accounts. IBM’s 2025 CEO study found that 25% of AI initiatives delivered the expected return. The usual causes are no baseline, no owner, and no link to the systems people use. A 100-day plan fixes those first.
Before day 0: use what diligence found
If the deal team ran AI due diligence, start from its output: the sized workflows, the red flags and the open questions. If not, run the free AI Due Diligence Checklist with management in the first week. It sorts the workflows into days 0 to 30, 31 to 60 and 61 to 100.
Days 0 to 30: baseline and selection
Do four things.
- Name the sponsor. One executive answers for the result.
- Test data access. Ask for 30 real records from each process in five business days.
- Record the baseline. For each candidate process, measure volume, time per item, cost and error rate. See how to set a baseline.
- Pick two or three workflows. Rank on dollars, data readiness and owner. Size them with the AI Opportunity Finder.
The output is one page: the workflows, the owners, the baselines and the dollars at stake in a conservative case.
Days 31 to 60: build
Build the workflows into the CRM, ERP or support desk the company already runs. Do not add a new platform for people to learn.
- Keep a person at each point where work goes to a customer, a vendor or a system of record.
- Run the new workflow next to the old one for a short period, and compare the results.
- Track adoption each week. A workflow that handles half the volume gives about half the benefit.
Days 61 to 100: measure and report
Measure each workflow against its baseline, with the same definitions and the same reports.
- Hard savings: which cost stopped, and in which month.
- Revenue gained: which metric moved. Count it at contribution margin.
- Hours saved: time back, with the plan to redeploy them.
Label each figure run-rate or realized. The board will ask which. See run-rate and realized AI savings.
What goes in the value creation plan
Only hard savings and revenue at contribution margin go in the EBITDA line. Hours saved go in a note. Each line has an owner, a start month and the evidence behind it.
At day 100, decide the next wave. Extend what worked and stop what did not. If the fund owns similar companies, write up each workflow that worked so the next company starts faster. The Portfolio AI Value Map ranks where to go next.
The plan on one page
| Phase | Work | Output |
|---|---|---|
| Days 0 to 30 | Sponsor, data test, baseline, selection | Two or three sized workflows with owners |
| Days 31 to 60 | Build in existing systems, with review points | Workflows in use on real volume |
| Days 61 to 100 | Measure, report, decide | Dollars against baseline, and the next wave |
The 100-day AI plan playbook has the week-by-week steps, checklists and a fill-in template. The glossary defines the terms.